This page provides further information about the status of an Internode DSLAM build.
DSLAM Status
| Planned |
We intend to build in the exchange |
Business case approved; pending construction approval |
| Build Preparation |
Construction work is being arranged |
About 2-4 weeks |
| In Build |
Construction is underway in this exchange |
About 18-24 weeks |
| In Build - Delayed |
Circumstances beyond the control of Internode mean that construction of this exchange is currently delayed. Typically caused by other carriers engaged in work ahead of Internode in the build queue. |
Indeterminate |
| In Build - Waiting |
Internode is waiting for one or more organisations to complete their build process in this exchange before Telstra allow Internode to commence their construction work. |
Indeterminate |
| In Test |
Testing, if required, prior to deployment |
About 1-4 weeks |
| Active |
Exchange is fully active |
Order Extreme® ADSL2+ now! |
| Active - No Free Ports |
We're currently out of ports or interconnect cabling and are working with Telstra to get more installed |
About 8-12 weeks |
Important Information - Please Read
- This table is for illustrative purposes only and does not represent a commitment in terms of time frames for exchange enablement.
- Time frames for all build phases represented in this table are subject to the potential of change or indefinite delay due to circumstances beyond the control of Internode.